About the Project

A total of 6 residential buildings which include 308 apartments and some commercial spaces in a neighbourhood in central Brussels. The project has 2 underground storeys for car parking and a total area of 27,000m2.

OJP made the foundations with footings and beams, the retaining walls with pre-fabricated elements and a circular subterranean ramp; mixed superstructure with some concrete elements made in situ and others in pre-fabricated concrete (slabs, pillars and walls); pre-fabrication of reinforced concrete beams to be inserted later, under construction; insertion of staircases and balconies in pre-fabricated concrete; masonry of exposed concrete blocks and concrete blocks to be overlaid; 100% of the solid ceramic brickwork on the facades of the whole building.

Client:

INTERBUILD N.V.

Duration of the Project:

23 months (on going)

Location:

Brussels, Belgium